Bug 23382: hours_between should match the logic of days_between
The loops for subtraction holiday dates in hours_between and days_between differed and as such their handling of start and end boundaries for days also differed. This patch makes them handle the boundary days consistently. Signed-off-by: Jonathan Druart <jonathan.druart@bugs.koha-community.org> Signed-off-by: Nick Clemens <nick@bywatersolutions.com> Signed-off-by: Martin Renvoize <martin.renvoize@ptfs-europe.com>
This commit is contained in:
parent
bbdee010aa
commit
a693c7243c
1 changed files with 4 additions and 8 deletions
|
@ -344,21 +344,17 @@ sub hours_between {
|
|||
# However for hourly loans the logic should be expanded to
|
||||
# take into account open/close times then it would be a duration
|
||||
# of library open hours
|
||||
# start and end should not be closed days
|
||||
my $skipped_days = 0;
|
||||
for (my $dt = $start_dt->clone();
|
||||
$dt <= $end_dt;
|
||||
$dt->add(days => 1)
|
||||
) {
|
||||
if ($self->is_holiday($dt)) {
|
||||
++$skipped_days;
|
||||
}
|
||||
while( $start_dt->compare($end_dt) < 1 ) {
|
||||
$start_dt->add( days => 1 );
|
||||
$skipped_days++ if $self->is_holiday($start_dt);
|
||||
}
|
||||
if ($skipped_days) {
|
||||
$duration->subtract_duration(DateTime::Duration->new( hours => 24 * $skipped_days));
|
||||
}
|
||||
|
||||
return $duration;
|
||||
|
||||
}
|
||||
|
||||
sub set_daysmode {
|
||||
|
|